Coordinate domains, Supabase, providers, monitoring, backup verification and the final go/no-go decision.
Release principle
A completed source package is not the same as a verified production system. Every critical external dependency needs live evidence and an accountable owner.
Go-live sequence
Complete the sequence in a controlled maintenance window.
Freeze release candidate and record the checksum
Apply Supabase migrations and run RLS tests
Configure production domains and SSL
Verify email, social, AI and SWICH sandbox integrations
Complete backup restoration drill
Enable monitoring and test alerts
Run smoke tests
Approve the go/no-go record
Rollback
Keep the previous Vercel deployment, database migration rollback notes and a current backup available until the release is stable.